LHSC sues over alleged window replacement problems in latest action involving former executive

London Health Sciences Centre (LHSC) is suing a contractor, an architectural firm and a former hospital executive over alleged problems with a window replacement project at Victoria Hospital. The hospital is seeking at least $2 million in damages, alleging the

Illustrative imageIllustrative image

London Health Sciences Centre (LHSC) is suing a contractor, an architectural firm and a former hospital executive over alleged problems with a window replacement project at Victoria Hospital.

The hospital is seeking at least $2 million in damages, alleging the contractor was paid for work it didn't complete and installed windows that were deficient and susceptible to water leaks.

The lawsuit, filed Nov. 9 in Ontario Superior Court, names BH Contractors Ltd., former LHSC vice-president of facilities management Dipesh Patel and Matter Architectural Studio Inc. It's the latest legal action stemming from LHSC's investigation into past procurement and financial practices.

Patel is already named in a separate $50-million lawsuit LHSC filed in July 2025, alleging a decade-long scheme involving fraudulent procurement practices and the misuse of public funds.

At the time, hospital supervisor David Musyj said a forensic audit had identified alleged fraudulent activity between 2013 and 2024. The hospital also filed a separate $10-million lawsuit against three former senior executives, alleging they failed to act on concerns about the practices. Those allegations have not been proven in court.

The latest lawsuit concerns window replacement work at Building 26, which houses the C and D towers at Victoria Hospital.

The project was supposed to replace window systems on the third through seventh floors. But LHSC alleges the work was largely limited to the third floor, where existing window frames were left in place, and some installations were deficient, allowing water to penetrate the building.

The lawsuit alleges BH Contractors quoted and invoiced the hospital for replacing 193 windows, but an investigation found only 99 had been replaced. LHSC said it paid the contractor more than $1.84 million, including HST, for work on the third floor alone.

The claim also alleges Patel took over administration and oversight of the project without consulting others at LHSC, approved invoices without adequate supporting documentation and failed to disclose a personal or financial interest in BH Contractors.

LHSC further alleges Matter Architectural Studio failed to properly assess the contractor's qualifications and compliance with procurement requirements before recommending it for the project.

The hospital said it must now remove and replace the windows installed on the third floor and complete the work that was never done on the fourth through seventh floors.

In a letter to the community published Wednesday, Musyj said the hospital is seeking to understand what took place.

"Our responsibility is to understand what happened, address the identified problems, and pursue recovery of funds that belong to the hospital and the communities we serve," he wrote.

Musyj said there are no immediate safety concerns related to the windows, but the legal action is necessary to protect the long-term integrity of the hospital's facilities. He acknowledged the continued revelations could be frustrating and disappointing for the community.

"That we continue to uncover past issues of this nature underscores the importance of the changes we have been making to governance, procurement, financial controls, and oversight at LHSC," he wrote.

CBC News contacted Patel's lawyer, Andrew Max, who said his client would not comment because the matter is before the courts.

CBC News was unable to reach BH Contractors at the phone number listed for the company, which was out of service. CBC News also requested comment from Matter Architectural Studio but had not received a response by the time of publication.

The allegations in the latest lawsuit have not been proven in court.

Other window replacement litigation

The Victoria Hospital lawsuit is not the first legal action involving alleged problems with window replacement work at LHSC.

In September 2025, the hospital filed a separate lawsuit concerning the University Hospital window replacement project, which involved about 1,270 windows.

That statement of claim seeks $40 million in total damages, $20 million from architectural firm HDR and an architect, and another $20 million from the contractor and subcontractors. LHSC alleges negligence and breach of contract, citing problems including water leaks, missing or inadequate gaskets, loose fasteners and deficient sealant.

The hospital has since moved forward with plans to replace more than 1,350 windows at University Hospital.

In total, the four separate lawsuits, including the $50-million and $10-million actions filed in July 2025, the $40-million University Hospital action and the new $2-million Victoria Hospital action, seek at least $102 million in damages.

LHSC said it will continue to address deficiencies identified in its reviews of past construction projects and share updates while respecting the court process.